Chargeback Management Workflow

Step-by-Step Instructions:

1. To see your chargebacks:

➤ Log in to your Merchant Portal

➤ Click on “Chargebacks” in the top menu. ➤ You'll land on the list of all chargebacks across your shops.

➤ By default, the list is sorted by Time to answer, so the most urgent cases appear first.

➤ Expiring soon (highlighted in red) means the chargeback will shortly become unavailable for defending. Once the time is up, the case can no longer be disputed.

➤ A dash (—) in the Time to answer column means no action is currently required from you on that case.

➤ There is no fixed deadline for all chargebacks: the time you must answer depends on the chargeback type and the card network. Always rely on the Time to answer value shown for the case.

2. Sorting the list

➤ You can sort the list by:

Time to answer — how much time is left to respond.

Chargeback date — the date the chargeback was received.

Creation date — the date of the original transaction.

3. Filtering by status

➤ All new chargebacks arrive in the Action required status — they require a decision from you: defend or accept.

➤ Use the status chips above the table for a quick filter: Accepted, Rejected, Action required, In progress, Won, Lost, Reversed.

The chargeback statuses you can see in the portal:

Action required — waiting for an action from you.

In progress — the case is under review by a third party.

Rejected — your defense documents were not accepted. New documents must be uploaded.

Accepted — liability was accepted by you.

Won — the chargeback was won.

Lost — the chargeback was lost.

Reversed — the chargeback was reversed by the issuing bank.

4. Selecting the period

➤ The bar above the table shows the selected Chargeback date period and the time the data was last updated. Use the refresh icon next to it to reload the results.

➤ To change the time period, use the filters.

5. Quick search

➤ Use the search field to find a chargeback by Order ID, Merchant Order ID and ARN.

6. Additional filters

➤ Click the filter button next to the search field to open additional search fields — amount and currency, stage and status, shop, payment and card details, customer email, merchant order ID.

➤ Click Apply to apply them, Reset to clear them, Close to hide the panel.

7. Share feedback

➤ The grey button on the right opens the Share feedback form. Ask a question, report a problem, or share an idea — your message goes directly to the xpate product team.

8. Open a chargeback

➤ Clicking on a chargeback row will open a detailed view in a new page.

➤ This page will show complete Dispute Details and Transaction Details.

9. Review the chargeback information

➤ Clicking on a chargeback row will open a detailed view in a new page.

➤ This page will show complete Dispute Details and Transaction Details.

➤ Check the reason (e.g. Services not received, Fraud, etc.).

➤ Look at the amount, chargeback date, and the time remaining to answer.

➤ Review the transaction linked to the chargeback for additional context: Transaction date, Card network, Order ID, Sale reference.

10. Choose how to respond

At the top of the detail page, you'll see two main action buttons:

✅ Accept Liability — Choose this if you agree with the chargeback and won't provide defense evidence.

❌ Defend Dispute — Choose this if you want to provide supporting documents to challenge the chargeback.

Tip: Always review the reason and check your documentation (e.g. receipts, customer communication, delivery proof) before deciding.

11. Follow the prompts to submit your decision

➤ If you choose "Defend Dispute", upload the required evidence as instructed.

➤ For VISA disputes please select the reason "Not listed" from the response reason drop-down.

➤ For Mastercard chargebacks please select "See Corresponding Documentation/Chargeback Remedied".

➤ For duplicate chargeback, please select "Duplicate Chargeback".

➤ Please add short comments and submit your evidence. For example: "Services were fully provided".

➤ You will see a pop-up window with a confirmation.

➤ If you choose "Accept Liability", the case will be closed, and the amount will not be recovered.

Important Notes:

➤ You must act within the listed "Time to answer". If the deadline passes, the case will automatically close in favour of the cardholder.

➤ If your defence documents come back as Rejected, upload new documents while time to answer is still available.

➤ If you received a chargeback but the transaction was already refunded, please let us know and we will dispute it on your behalf. (Sometimes an issuer could raise a chargeback despite it already being refunded.)